Projects

Project Sunday - Hershey, PA

The Hershey Company

Liberty Excavators Inc.

Start Date: April 2024

Completion Date: April 2024

Jack & bore (3) 48” steel casing, 110’ in length under a Norfolk Southern railroad for storm water run-off.

2nd Street Gas Replacement - Emmaus, PA

Ugi Utilities Inc.

Great Western Services

Start Date: March 2024

Completion Date: March 2024

Jack & bore 100’ of 12” steel casing under a Norfolk Southern railroad for a gas line.

North Duck Creek Water Tower - Smyrna, Delaware

Town of Smyrna

Johnston Construction

Start Date: March 2023

Completion Date: April 2023

Five, 150’ jack & bores of 24” steel casing under Dupont Highway for utiliites.

Sewer Extension North of I-81 - Silver Spring Twp, Cumberland County, PA

Silver Spring Township Authority

Pact Construction Inc.

Start Date: March 2023

Completion Date: March 2023

Jack & bore 70’ x 24” steel casing for an 8” gravity sewer under Rt 944.

Colebrookdale Railroad - Boyertown, Pa

Colebrookdale Railroad

R.A.W. Excavating

Start Date: November 2023

Completion Date: November 2023

Jack & bore 25’ of 18” steel casing under the railroad for electrical conduits.

Lewis Twp Regionalization Project - Lewis & Delaware Twp, Northumberland County

Milton Regional Sewer Authority

HRI Inc.

Start Date: June 2023

Completion Date: September 2023

Directional drill 17,000’ of 4” and 1,600’ of 2” Hdpe low pressure sewer, along with 23 service laterals.

Conestoga Rd - Radnor Twp, Delaware County, PA

Aqua Pennsylvania

Brubacher Excavating Inc.

Start Date: June 2023

Completion Date: July 2023

Directional drill 165’ and 190’ of 20” Hdpe under streams along Conestoga Rd.

Meadows Rd Utilities - Lower Saucon Twp. Northampton County

Lower Saucon Twp.

Barrasso Excavation Inc

Start Date: April 2024

Completion Date: May 2024

Jack & bore 45’, 100’ and 125’ of 18” steel casing for 6” forcemain and 120’ of 24” steel casing for 12” D.I. waterline under a stream and road.

East Whiteland Twp. Sanitary Sewer - North Bacton Hill & Swedesford Rd, East Whiteland Twp., Chester County, PA

Aqua Pennsylvania Wastewater Inc.

Brubacher Excavating Inc.

Start Date: April 2024

Completion Date: April 2024

Directional drill 2,586’ of 2” Hdpe low-pressure sewer.

Green Briar Rd Water Line Tie-Inhri - Conewago & Manchester Township, York County, PA

York Water Company

Start Date: July 2023

Completion Date: July 2023

Directional drill 350’ x 16” fusible Pvc for a waterline under the Little Conewago Creek.

Pequea Valley Sewer & Water Extension - Gordonville, PA

Pequea Valley School District

Wexcon Inc.

Start Date: April 2023

Completion Date: August 2023

Directional drill 5,000’ of 10” Hdpe waterline and 5,000’ of 3” sewer forcemain along Rt 772.

Washington County 16” Forcemain - Maugansville Rd, Hagerstown, MD

HRI Inc.

Start Date: April 2024

Completion Date: April 2024

Directional drill 200’ of 16” Hdpe sewer forcemain.

Morwood Area Sanitary Sewer System - Franconia Sewer Authority

Morwood Area Sanitary Sewer System Franconia Sewer Authority

Phone: 215-723-1137

Pact Construction Inc.

Phone: 908-788-1985

Start Date: July 2019

Completion Date: April 2020

Directional drill approx. 30,000’ of 2”,3” and 4” L.P. HDPE sewer. Average depth 4 to 6 feet.

Fair Hill Water System Upgrade - Maryland Dept. of Natural Resources

Fair Hill Water System Upgrade – Maryland Dept. of Natural Resources

Phone: 410-398-1246

M-2 Construction

Phone:  717-305-8801

Start Date: November 2019

Completion Date: March 2020

Directional drill 2”,4”6” and 10” FPVC waterline. Average depth 4 to 6 feet.

Sadsbury Commons - PH & C LLC Land Development

Sadsbury Commons – PH & C LLC Land Development

Phone: 484-383-3326

PH & C Land Development

Phone: 484-383-3326

Start Date: July 2019

Completion date: October 2020

Install 3,720’ of 6” Hdpe sewer force main. Average depth 4 to 6 feet.

Pennsylvania Turnpike Fiber Optic Network Project

Pennsylvania Turnpike Fiber Optic Network Project

Black & Veatch Construction Inc.

Phone: 913-359-1622

Start Date: April 2022

Completion Date: September 2022

Install approx. 17,000′ of 4″ Hdpe conduit for fiber optic cable.

Emergency Waterline Break Replacement - Penn Bernville Elementary School

Penn Bernville Elementary School

A.H. Moyer Inc.

Phone: 717-866-2103

Start Date: February 2022

Completion Date: February 2022

Install 480′ of 6″ Hdpe waterline to replace a broken section of watermain to the Penn Bernville Elementary School.

Mt Carbon Truss Bridge waterline relocation - Pottsville, PA

Schuylkill County Municipal Authority

Barrasso Excavation Inc.

Phone: 610-987-0025

Start Date: February 2022

Completion Date: February 2022

Directional drill 260′ of 14″ DR-9 Hdpe waterline under the Schuylkill River.

Schoolhouse Rd SR 1007 low pressure construction - Franconia Twp. PA

Franconia Sewer Authority

Doli Construction

Phone: 215-997-8026

Start Date: January 2022

Completion date: January 2022

Install 4,100′ of 4″ / 1,710′ of 2″ low pressure sewer lines.

SECCRA SR 41 Project - West Grove, PA

SECCRA

Wexcon Inc.

Phone: 610-488-7420

Start Date: December 2021

Completion Date: December 2021

Jack & bore 90′ of 36″ steel casing under SR. 41 for a storm water improvement project.

Arcona Railroad Crossing - Mechanicsburg, PA

Ugi Utilities

Phone: 717-255-1437

Start Date: July 2022

Completion Date: July 2022

Jack & bore 150′ of 24″ steel casing under a Norfolk Southern Railroad for a gas line. This bore was primarily in limestone rock.

Arsenal Rd & 11th Ave waterline in York County, PA

York Water Company

Phone: 717-845-3601

Start Date: January 2022

Completion Date: February 2022

Directional drill 475′ of 16″ FPVC casing pipe to house a 12″ FPVC waterline

Cedar Brook Country Club Water Service in Blue Bell, PA

Cedar Brook Country Club

Phone: 215-646-9410

KBC Construction

Phone: 215-397-5334

Start Date: January 2022

Completion Date: January 2022

Directional drill 1,200′ of 6″ and 4″ Hdpe waterlines.