Projects

Sweigart Farms, Mt Joy, PA

Sweigart Farms

Twighlight Renewables

May 2025

Directional drilled 230’ of (2) 3” and a 1” electric conduit under a dairy barn.

19th Ward Pump Station Forcemain Project, Reading, PA

City of Reading

JOAO Bradley Construction

Started early February 2025, completed late March 2025

Directional drilled 525’ of 16” HDPE Forcemain under the Schuylkill River at a maximum depth of 28’ below the riverbed. Subsurface conditions consisted of mostly rock.

Peck Rd over Shamona Creek Project, Downingtown, PA

Aqua Pennsylvania Inc.

Brubacher Excavating Inc.

Started early July 2024, completed late July 2024

Directional drilled 496’ of 12” HDPE waterline in mixed soil and rock conditions under a tributary of the Shamona Creek.

Project Sunday - Hershey, PA

The Hershey Company

Liberty Excavators Inc.

Start Date: April 2024

Completion Date: April 2024

Jack & bore (3) 48” steel casing, 110’ in length under a Norfolk Southern railroad for storm water run-off.

2nd Street Gas Replacement - Emmaus, PA

Ugi Utilities Inc.

Great Western Services

Start Date: March 2024

Completion Date: March 2024

Jack & bore 100’ of 12” steel casing under a Norfolk Southern railroad for a gas line.

North Duck Creek Water Tower - Smyrna, Delaware

Town of Smyrna

Johnston Construction

Start Date: March 2023

Completion Date: April 2023

Five, 150’ jack & bores of 24” steel casing under Dupont Highway for utiliites.

Sewer Extension North of I-81 - Silver Spring Twp, Cumberland County, PA

Silver Spring Township Authority

Pact Construction Inc.

Start Date: March 2023

Completion Date: March 2023

Jack & bore 70’ x 24” steel casing for an 8” gravity sewer under Rt 944.

Colebrookdale Railroad - Boyertown, Pa

Colebrookdale Railroad

R.A.W. Excavating

Start Date: November 2023

Completion Date: November 2023

Jack & bore 25’ of 18” steel casing under the railroad for electrical conduits.

Lewis Twp Regionalization Project - Lewis & Delaware Twp, Northumberland County

Milton Regional Sewer Authority

HRI Inc.

Start Date: June 2023

Completion Date: September 2023

Directional drill 17,000’ of 4” and 1,600’ of 2” Hdpe low pressure sewer, along with 23 service laterals.

Conestoga Rd - Radnor Twp, Delaware County, PA

Aqua Pennsylvania

Brubacher Excavating Inc.

Start Date: June 2023

Completion Date: July 2023

Directional drill 165’ and 190’ of 20” Hdpe under streams along Conestoga Rd.

Meadows Rd Utilities - Lower Saucon Twp. Northampton County

Lower Saucon Twp.

Barrasso Excavation Inc

Start Date: April 2024

Completion Date: May 2024

Jack & bore 45’, 100’ and 125’ of 18” steel casing for 6” forcemain and 120’ of 24” steel casing for 12” D.I. waterline under a stream and road.

East Whiteland Twp. Sanitary Sewer - North Bacton Hill & Swedesford Rd, East Whiteland Twp., Chester County, PA

Aqua Pennsylvania Wastewater Inc.

Brubacher Excavating Inc.

Start Date: April 2024

Completion Date: April 2024

Directional drill 2,586’ of 2” Hdpe low-pressure sewer.

Green Briar Rd Water Line Tie-Inhri - Conewago & Manchester Township, York County, PA

York Water Company

Start Date: July 2023

Completion Date: July 2023

Directional drill 350’ x 16” fusible Pvc for a waterline under the Little Conewago Creek.

Pequea Valley Sewer & Water Extension - Gordonville, PA

Pequea Valley School District

Wexcon Inc.

Start Date: April 2023

Completion Date: August 2023

Directional drill 5,000’ of 10” Hdpe waterline and 5,000’ of 3” sewer forcemain along Rt 772.